Screen easily, even at high flow rates, with unequaled solids suspension.
DRILPLEX mud system allows drilling 311.1mm section without lost circulation in record-breaking time
已发表: 01/01/2010
DRILPLEX mud system allows drilling 311.1mm section without lost circulation in record-breaking time
已发表: 01/01/2010
Well Information |
|
| Location | Irkutsk Region, Eastern Siberia, Russia |
| Field | Verkhnechonsk |
| Number of wells | 1 |
| Interval drilled | Conductor |
| Interval length | 485m |
The Situation
Drilling of the conductor interval for one of the Verkhnechonsk wells was complicated by partial losses to total lost circulation. This caused increase in well construction time for this interval. At the planning stage M-I SWACO specialists carried out measures on losses elimination through mixing and pumping pills with Kwik Seal, Nut Shell, Mica, and Reamix. These pills had different formulations and limited volumes due to the application of the MWD and mud motor in the bottom-hole assembly which prevented elimination of the lost circulation problem.
The Solution
M-I SWACO suggested changing the drilling fluid system from the polymer-clay mud to the highly shear-thinning DRILPLEX system that was specially designed for drilling lost-circulation reservoirs. At the design and modeling stage it became clear that DRILPLEX unique rheology alone could not reduce ECD to a significant extent in the lost-circulation zones. Thus the drilling fluid specific gravity was reduced from 1.10g/cm3 to 1.02g/cm3.
All required chemicals were delivered for pilot testing in a record time after the end of navigation.
The Results
The conductor section was drilled with a 311.1mm bit without any lost circulation problems. The application of the DRILPLEX system provided the following benefits:
- Elimination of mud losses
- The highest cost/performance ratio of drilling operations, together with the application of the Smith bits
- Elimination of any other complications due to the absence of FLOPLEX† starch that increased the drilling fluid filtration.
- Casing pipe cementing without lost circulation accompanied by cement returns to the wellhead.
“Using DRILPLEX? allowed drilling the conductor section of the well without lost circulation and in a maximum short time, setting a total record drilling time for the Verkhnechonsk field.”S.A. Fatkulin, Lead Drilling Engineer, VerkhnechonskNefteGaz OJSC