Acquire borehole seismic measurements for real-time, time-depth-velocity information without disrupting drilling operations.
Seismic-while-drilling service resolves depth uncertainty offshore Southeast Asia
Resolve uncertainty about depth of carbonate reservoir to set casing within 20 m of the formation top for successful well construction
Set casing on top of offshore carbonate formation
An operator in Southeast Asia drilling an offshore vertical exploration well wanted to avoid accidental penetration of the carbonate reservoir near the 12¼-in hole section because it could lead to a kick and possible loss of the well. Successful completion of the well required setting the 9⅝-in casing within 20 m of the top of the carbonate formation—and there was a ±50-m uncertainty about its depth, despite the availability of a 3D prestack depth migration and offset well data.
Update depth prediction of formation top
果冻传媒 used seismicVISION™ seismic-while-drilling service to update depth prediction at every connection, accurately geostopped 12¼ in hole section, and set 9⅝ in casing as planned.
The seismicVISION service was selected to acquire real-time checkshots and images for updating the predicted depth of the formation top. Because the checkshots were acquired during connections for best acoustics, a minimal amount of rig time was required.
After the seismic level had been acquired at a connection, windowed real-time waveforms were transmitted uphole using mud pulse telemetry. The checkshots were then processed from the waveforms at the wellsite, and real-time depth updates were calculated while drilling continued. A real-time corridor stack processed from the real-time waveforms showed the seismic position. Extrapolating a depth projection to the formation top from the look-ahead (reflectivity) information enabled the drilling team to geostop the 12¼-in section before it penetrated the carbonate formation.
Set casing without penetrating formation top
Using seismicVISION service to revise the depth prediction in real time at every connection, the drilling team resolved the ±50-m uncertainty about the depth of the carbonate reservoir and geostopped the 12¼-in section before it penetrated the formation top. The 9⅝-in casing was set within 20 m of the formation top, as was required for successful completion of the well.