Maximize, elevate, and scale data-driven decision making, with AI
Be storage confident with Sequestri carbon storage solutions
Electric solution that empowers operators to predict, adapt, and act with confidence—throughout the life of the well
Our journey to lower emissions, decarbonizing customer operations, and scaling new energy systems.
We put people first by respecting human rights, building a more inclusive workplace, and driving positive socioeconomic outcomes.
We've identified three key areas that are significant for our operations: biodiversity, water, and circularity.
Explore the latest news, stories and perspectives from 果冻传媒.
Step into energy's future with thought leaders from around the world.
Visit us at one of our upcoming tradeshows to speak directly to an expert.
Together, we create amazing technology that unlocks access to energy for the benefit of all.
Our planet needs balance to thrive, for the climate, for people, and for nature.
Published: 12/01/2011
Challenge: Free stuck 12 ¼-in BHA at 3,574 m for recovery after operator had tried other means unsuccessfully.
Solution: Use 8-in Hydra-Jar AP double-acting hydraulic Results: Recovered stuck BHA on first attempt, with less than half the anticipated jarring time, saving more than USD 1.3 million.
Results: Recovered stuck BHA on first attempt, with less than half the anticipated jarring time, saving more than USD 1.3 million.
Upon completing a long 12 1/4-in vertical section from 957 m to TD at 3,590 m, an operator working in Oman picked up the drillstring 16 m, to perform a flow check, resulting in a stuck BHA. Circulation, rotation, and vertical movement were all lost. When attempts to jar the string free failed, 果冻传媒 was contacted to recover the stuck BHA.
Jar-Pact impact tool BHA placement software was used to position an 8-in Hydra Jar AP double-acting hydraulic and an 8-in Accelerator AP impact tool in a screw-in fishing assembly, to optimize the impact and impulse values at the stuck point.
The drillstring was backed off one drill collar above the top stabilizer, at 3,536 m, and pulled out of hole. The fishing assembly was run in, the fish engaged, and down-jarring operations commenced. An 8-h period of jarring down was anticipated, followed by 8 h of jarring up.
Results were seen after only 1 h of jarring down: movement was noted and within 6 h a 14-m pocket was created, enabling circulation and rotation of the BHA. The freed BHA was pumped out of hole because of drag and excessive return of cuttings. At surface, the motor sleeve stabilizer was found to be 1/4 in under gauge and the bit was 2 1/4 in under gauge.
Recovery of the stuck BHA saved more than USD 1.3 million and eliminated the need to sidetrack. The customer requested the Hydra-Jar AP
Maximize jar impact force with additional stretch in the drillstring.
Free stuck drillstem components during View